Norway · Distribution planning · Case 01
Can this feeder supply electric steam?
Switch the boiler connection to see which cable limits additional demand. The calculation uses 40 customer meters across all 8,760 hours of 2021.
Loading the verified study results…
What should the factory do?
See the connection results above.
For the downstream connection, doubling the cable with an identical parallel circuit also permits direct steam. Compare its annualised installed cost with the storage premium shown below. Both options deliver 16,068 MWh of useful heat per year.
Method and assumptions
Balanced radial AC power flow on a 10 MVA base. Historical loads use an assumed 0.95 lagging power factor. The electric boiler has unity power factor and 98% efficiency. Each hour is checked against 0.94–1.06 per-unit voltage and known continuous cable ratings. The first listed critical hour may tie other hours.
The data authors use 1,000 MVA for unknown equipment ratings. The ideal source and unknown transformer ratings make these results conditional upper bounds. Meter values are hourly averages. A connection decision also requires the operator’s ratings, contract limits and protection assessment.
The illustrative factory requires 4.5 MW of useful steam on weekdays from 08:00 through 15:59 and 1 MW otherwise. Options use a 6 MW electric boiler, an optional 8 MWh steam accumulator, cyclic inventory, 0.1% hourly standing losses and free discharge up to the process demand. We assume €70/MWh electricity and €8,000 per MWh of storage capacity per year. Costs cover electricity and incremental equipment only. Common boiler cost, location-specific civil works, taxes and demand charges are excluded. Connection routing costs can change the ranking.